Islamabad’s E-12 sector development passes 68% after decades-long halt

Islamabad’s E-12 sector development passes 68% after decades-long halt

Islamabad’s E-12 Sector Development Reaches 68% Completion

The Capital Development Authority (CDA) reports significant progress in the development of Sector E-12, with work now at 68% completion after a decades-long halt. The CDA is handing over plots to allottees as road, drainage, and utility work continues across the four sub-sectors, following the retrieval of approximately 1,135 kanals of encroached land.

According to the CDA, street development is at varying stages:

  • In E-12/1 and E-12/2, TST (triple surface treatment) has been completed in 25 and 31 streets, respectively.
  • In E-12/3, 15 streets have had the treatment done, while earthwork and base construction are ongoing in the remainder.
  • E-12/4 has completed earthwork, and work on base, sub-base, drainage, and sewerage systems is in progress.

The authority has finished earthwork, base, sub-base, and drainage work on the eastern service road, with asphalting now underway along Khayaban-i-Iqbal. Similar work is also progressing on Margalla Road, after the completion of its base, sub-base, drainage, and sewerage infrastructure. Underground work for electricity supply is also in progress, and landscaping and plantation in green belts are being carried out.

CDA Chairman Sohail Ashraf has directed formations to remove impediments and complete remaining work on a priority basis, emphasizing the authority's focus on developing new sectors and providing better residential facilities to address Islamabad's growing housing needs.