Peshawar Road underpasses targeted for completion by month-end, commissioner told

Peshawar Road underpasses targeted for completion by month-end, commissioner told

Peshawar Road Underpasses Progress Update

RAWALPINDI, (Pakistan Point News - 19th Nov, 2026) Commissioner Rawalpindi Salman Ghani visited the construction sites at Race Course Chowk and Charing Cross underpasses on Peshawar Road on Thursday to review the progress of the ongoing development work.

During the briefing, it was shared that:

  • Race Course Underpass: 74% complete.
  • Charing Cross Underpass: 71% complete.

The remaining work is expected to be finished by the end of the current month.

Key construction activities, such as piling, deck slabs, capping beams, barrier installation, underpass excavation, utility relocation, and drainage works, have largely been completed at both sites.

The Race Course Underpass will feature two lanes for northbound traffic and a three-level road configuration for efficient traffic movement and turning.

Commissioner Salman Ghani's Directives:

  • Strictly adhere to construction quality standards.
  • Complete remaining work within the given timelines.
  • Ensure smooth traffic flow, effective alternative routes, and minimal public inconvenience throughout the construction process.
  • Implement regular anti-smog measures to control dust and air pollution.

Salman Ghani emphasized that upon completion, these underpasses will make Rawalpindi's main traffic corridor nearly signal-free, substantially easing traffic congestion for commuters.

The Superintending Engineer of the Highways, Communication and Works Department, along with other relevant officials, accompanied Commissioner Ghani during the site visit.