ISLAMABAD, (APP - UrduPoint / Pakistan Point News - 21st Sep, 2026) A study on the "Optimal Siting of Grid-Scale Battery Energy Storage Systems (BESS) in Pakistan" has suggested a data-driven national roadmap to deploy storage technology and ease mounting grid constraints in the country.

Conducted by the Sustainable Development Policy Institute (SDPI) in collaboration with Network for Clean Energy Transition (NCET), the study was launched on Monday.

The event, held at SDPI, brought together experts, regulators, and researchers to discuss how BESS can:

  • Enhance grid flexibility
  • Integrate Variable Renewable Energy (VRE)
  • Reduce curtailment
  • Address transmission bottlenecks

As Pakistan pursues its clean energy transition.

Dr Kashif Imran, a Professor at the US-Pakistan Centre for Advanced Studies in Energy, National University of Science and Technology (NUST), stated that the study offers valuable insights into optimal BESS siting but noted continuing confusion regarding its deployment across the sector. He recommended a three-tier approach to facilitate investors.

He also highlighted:

  • The need to harness data analytics more effectively, as the study, though transmission-focused, was conducted with limited available data.
  • That BESS could reduce transmission losses and address voltage fluctuations, but its applications should be combined to meet specific grid needs.
  • The TOPSIS method as an option for guiding BESS site selection and the importance of reverse power flow analysis.

Muhammad Umer, Research Associate at SDPI, presented the study findings, noting that Pakistan's power sector continues to face persistent Energy Not Served (ENS) losses amounting to 2.77 GWh.

He outlined the study's key objectives:

  • Developing a data-driven siting framework for BESS
  • Mitigating congestion and curtailment
  • Building a business case aligned with CPEC 2.0 investments
  • Formulating a policy and regulatory roadmap

Umer further explained that the research involved screening National Grid Company's 500 kV and 220 kV grid stations, using ranking-based methodology to assess candidate sites for optimal BESS deployment - including Shikarpur, Faisalabad, Dadu, and Rawat - based on technical and locational parameters.

Outlining policy recommendations, Umer called for:

  • Mandating BESS modeling in the Indicative Generation Capacity Expansion Plan (IGCEP)
  • Integrating BESS into Transmission System Expansion Planning (TSEP) cycles
  • Adopting bottom-up forecasting
  • Establishing a national framework for monitoring and evaluating BESS deployment.