Commissioner Reviews Quetta Development Package; Orders Timely Completion Of Key Road Projects
Quetta, (APP – UrduPoint / Pakistan Point News – 15th Sep, 2026)
Commissioner Zeeshan Lashari chaired a meeting to review the progress of ongoing and new projects under the Quetta Development Package (QDP), focusing on funding, implementation, and overcoming obstacles.
Meeting Details:
- Attendees: Deputy Commissioner Quetta Mehrullah Badini, Deputy Commissioner Quetta West Munir Ahmed Durrani, Divisional Director Development Zahoor Ahmed, Deputy Project Director QDP Muhammad Abid, and other officials.
- Key Discussion Points:
- Project progress updates from the Deputy Project Director.
- Fund allocation.
- Challenges faced in project implementation.
Commissioner’s Directive:
Commissioner Zeeshan Lashari emphasized that the Quetta Development Package is a vital initiative aimed at:
- Resolving traffic congestion.
- Providing improved travel facilities to citizens.
- Transforming Quetta into a modern city.
He directed:
-
Identification of Projects: All projects should be clearly identified on Google Maps for better location assessment and progress tracking in the next meeting.
-
Project Completion Timelines:
- Zarghoon Road from Hockey Chowk to Akram Hospital within one month.
- Sariab Service Road within two months.
-
Mosque Issue Solution: The Deputy Commissioner Quetta West will find a practical solution for mosque-related issues on Sariab Road to avoid further delays.
-
Underpass Progress Reporting: A detailed progress report is required on the Spini Sabzal Underpass construction.
-
Monitoring and Quality Control: Assistant Commissioners are directed to monitor all projects for quality, speed, and timely completion within deadlines.
New Schemes:
The package includes new schemes like:
- Airport Road Flyover
- Sariab Road Flyover
- Pedalastic Bridge on Airport Road
- Installation of underground cables on Airport Road
- Construction of a parking plaza for the AG Office.
Commissioner Lashari stressed that unnecessary delays will not be tolerated and obstacles must be promptly removed to deliver benefits of the package to citizens at the earliest.