Balochistan completes 4km desilting of Pat Feeder Canal

Balochistan Completes 4km Desilting Of Pat Feeder Canal

ISLAMABAD, (APP – UrduPoint / Pakistan Point News – 21st Aug, 2026)

Balochistan has completed desilting over a four-kilometre stretch of the Pat Feeder Canal as work progresses on Package-I of the canal system’s remodelling project.

According to documents available with Wealth Pakistan:

  • Package-I of the Remodelling of Pat Feeder Canal System, Balochistan, was awarded at a cost of Rs15.750 billion.

The documents highlight the following progress:

  • Desilting completed over four kilometres, with obstacles removed from the canal bed.
  • Concrete lining completed over one kilometre stretch.
  • Canal banks prepared over 2.3 kilometres.
  • Canal diversion work in progress over a seven-kilometre stretch.
  • Several preparatory activities, including joint survey, pre-construction survey, provision of accommodation facilities, laboratory establishment, and issuance of drawings, completed.
  • Land acquisition survey finished, with the award process ongoing.
  • Over 200 houses identified as encroachments within the canal’s right-of-way demolished.

The ongoing activities are part of Package-I of a broader Remodelling of Pat Feeder Canal System being undertaken by the Irrigation Department of the Government of Balochistan.

The remodelling aims to:

  • Improve irrigation efficiency,
  • Reduce water losses, and
  • Ensure a more reliable water supply to farmlands across Balochistan.

Once completed, the project is expected to strengthen agricultural productivity and support long-term water resource management in the province.