DG KDA reviews ongoing development work

DG KDA Reviews Ongoing Development Work

DG KDA reviews ongoing development projects in Karachi, including the Munwar Chowrangi underpass, Check Post Three to Malir Expressway (Shahrah-e-Bhutto), and Gujjar Nullah connectivity.

Project Details:

  • Gujjar Nullah Connectivity:

    • Cost: Rs. 2,554.431 million
    • Length: 9 kilometers
    • Road Width: 7.9 meters
    • Bridge Length: 583 meters
    • Bridge Width: 5.50 meters
  • Check Post 3 to Malir Expressway (Shahrah-e-Bhutto):

    • Cost: Rs 1,449.459 million
    • Length: 11.54 kilometers
    • Road Width: 7.3 meters
    • Bridge Length: 125 meters
    • Bridge Width: 8 meters
  • Munwar Chowrangi Underpass:

    • Cost (estimated): Rs. 1,485.150 million; (revised) Rs. 2,026.487 million
    • Length: 727 meters
    • Underpass Length: 493 meters
    • Main Carriageway Width: 7.3 meters (dual track)
    • Slip Road & Service Road: 2 lanes each (3.05 & 3.65 meters wide)

Key Takeaways:

  • DG KDA, Zain-ul-Abidin Ansari, emphasized quality and technical requirements in all development work.
  • He directed officials to prioritize timely project completion for better travel facilities to citizens.
  • Regular monitoring of field work is stressed for effective progress.